ABC Coke (continued)

Turnkey System

ABC Coke selected SEECO to design and install a turnkey system. SEECO designed and built the system with a minimum of customer-provided specifications. The turnkey project included all foundations, structural steel, piping, electrical, and instrumentation. Even the power building to house the equipment, including the water cooled condensers on the roof, was SEECO's responsibility.

The system runs 24 hours a day, generating around 90 percent of the plant's electrical energy needs. This amounts to a savings, on an annual basis, of more than $750,000. In addition, excess electricity produced by the system, primarily from the nighttime generation period, is sold to the local utility, producing even more savings.

According to Mike Osburn, manager boilers and power generation for ABC, the system has proven itself to be well-running and a significant contributor to the plant's economic performance.

 

 

 

 

SEECO's turnkey installation included the following elements, clockwise starting from 12 o'clock: cooling towers located on top of the power building (also SEECO's responsibility), low voltage motor control panel, condenser circulation pumps, high voltage power distribution and utility tie breaker, condenser hot well and condensate return pumps, and generator control panel.

   
1 2
   

 



Home | About Us | Services | Products | Case Studies | News | Municipal | Pump Controls | OEM | Contact Us | Members | Privacy Policy

2240 Rocky Ridge Rd.; Birmingham, AL 35216
800.536.2525; 205.824.0004; fax 205.824.0439