Objective:

A General Contractor contacted Revere to complete the Instrumentation & Control Design from the 60% design level to the 100% design level for its Wastewater Treatment Plant

 

Description of Services Provided:

  • Provided
    • Equipment Listing and Data Sheets
    • Division 17 Specifications
    • I/O Listing
    • Network Topology
  • Managed Vendor Packages and Electrical/Mechanical Disciplines
  • Installed Field Instrumentation
  • Provided PLC Control Panel Hardware and Drawings
  • Installed computer hardware/software
  • Designed software (Control Strategies and Graphic Displays)
  • Managed Control System test plan
  • Developed and implemented training plan
  • Provided spare parts and tools
  • Furnished operations & maintenance manuals
  • Programmed PLC
  • Configured HMI
  • Conducted FAT testing
  • Performed
    • Detailed I/O checkout
    • PLC Control Panels testing
    • Field instruments calibration
    • Establish communications & verification of functional control strategies
  • Coordinated with equipment suppliers